RADIO HILL GOLD CIRCUIT CONSTRUCTION UPDATE

 

Artemis Resources Limited (“Artemis” or “the Company”) (ASX: ARV) is pleased to provide this update on construction of the company’s 100% owned Radio Hill process plant.

 

 

 

A picture containing ground, outdoor

Description generated with high confidence

 

HIGHLIGHTS

 

-                      Construction works commenced on 20th August 2018

-                      Tertiary crusher installation works complete

-                      Crushed product screen and conveyer modifications complete

-                      Thickener and flocculant plant foundations complete

-                      New High Voltage (HV) power corridor complete

-                      Gekko circuit installation complete

-                      Gold Room structure and cladding complete

-                      Milling and classification area works commenced

-                      Internal plant electrical works commenced

-                      TSF3 approval submission to be made in October

-                      Secondary equipment refurbishment and site surface infrastructure works continue

 

Artemis’ Chief Executive Officer, Wayne Bramwell, commented:

After the initial delay associated with approvals, the construction and refurbishment work associated with the gold circuit will be completed next quarter. The Installation of this gold circuit at Radio Hill is Stage 1 of our strategic plan and begins the process to expand the multi-metal capability of the Radio Hill Operations.

 

OVERVIEW

Radio Hill Construction and Refurbishment Update

The Radio Hill processing plant is 35 km from Karratha in the Pilbara region of Western Australia. This base metal flotation concentrator and associated infrastructure was built in 1988.  Previous operators have invested more than $60m between 1988 and 2002 (Fox Resources 2004 Annual Report). In September 2002, Fox Resources (Fox) acquired the process plant and underground mine and associated mining leases.

The 425,000 t flotation concentrator produced copper and nickel concentrates from the Whundo Copper Mine and the Radio Hill underground for export. In mid-2008 Fox placed the Radio Hill Operations on care and maintenance due to weakening copper price which saw US$ copper prices fall to circa US$3,000 by the end of 2008.  In March 2017 Artemis Resources acquired the Radio Hill Operations, associated infrastructure and tenements from Fox for approximately $4M in cash and Artemis shares (refer ASX 2 March 2017).

 

In November 2017 Artemis appointed Process 26 Engineers and Constructors (“Process 26” - www.process26.com) to refurbish and upgrade the existing Radio Hill crushing and grinding circuits (announced 27 Nov 2017). Construction activities commenced on 20 August 2018 to upgrade the facility with the installation of additional crushing equipment, tailings dewatering facilities and a gold room. Gekko Systems (“Gekko” - www.gekkos.com) were mobilised to install and commission the gravity gold extraction circuit.

 

Works Progress to date

Process 26 and Gekko have advanced the following:

-                      Crushing circuit refurbishment program complete - including ROM wall replacement, installation of refurbished primary and secondary crushers, conveyor belts, and vibrating screen.

-                      Milling and Classification area – steelwork, cyclone cluster and DSM screen installation has commenced.

-                      Gekko gold circuit complete – including installation of Inline Pressure Jig, Falcon, Inline Spinner and associated gold room equipment (refer Figure 2).

-                      Gold room building – structure and cladding complete and and fit out continues with Gemini Table and Barring Furnace placed into position.

-                      All slurry pumps have been overhauled and installation underway.

-                      Thickener and flocculant plant - foundations and ground slabs complete with thickener lifted into place.

-                      High Voltage HV cables installed and awaiting termination.

 

 

 

A picture containing transport, sky, building

Description generated with very high confidence

 

 

 

A screenshot of a cell phone

Description generated with very high confidence

 

LOOKING FORWARD

The Stage 1 flowsheet for Radio Hill is depicted in Figure 3.

Process 26 construction teams continue to advance the mechanical installation in the milling and classification area, with particular focus on electrical connections and instrumentation. Electrical refurbishment and no load commissioning of the crushing, materials handling and grinding circuits will be completed next quarter with construction teams demobilising on completion. Artemis has approval to utilise geotubes under its existing operating licence and is currently finalising approval application documents for TSF3.

 

In parallel to construction activities Artemis continues to advance:

-                                TSF3 and TSF4 approval submissions;

-                                long term power supply options with Horizon Power and others;

-                                DMIRS approvals required for bulk sampling at several of its gold targets including Carlow

 

Castle and Nickol River;

-                                resource updates on the Weeriana Au and Carlow Castle Au-Cu-Co Projects, and

-                                conversion of Carlow Castle and 47K Patch to a mining lease.

 

For further information on this update or the Company generally, please visit www.artemisresources.com.au or contact:

 

Wayne Bramwell                                  

Chief Executive Officer                                        

Telephone: +61 417 953 073

 

Edward Mead                                        

Executive Director                                                

Telephone: +61 407 445 351

 

David Tasker                                         

AdvisorChapter One                                        

Telephone : +61 433 112 936

 

 

A close up of a sign

Description generated with high confidence

ASX : ARV

FRANKFURT : ATY

US OTC : ARTTF

GOLD AND COBALT IN THE PILBARA

 

ARTEMIS RESOURCES LIMITED IS AN AUSTRALIAN MINERAL DEVELOPER ADVANCING ITS WEST PILBARA BASE METALS, BATTERY AND PRECIOUS METALS ASSETS TOWARDS PRODUCTION.

ARTEMIS HAS CONSOLIDATED A MAJOR LAND HOLDING IN THE WEST PILBARA AND IS THE 100% OWNER OF THE RADIO HILL OPERATIONS AND PROCESSING INFRASTRUCTURE, STRATEGICALLY LOCATED 30 KM FROM THE CITY OF KARRATHA, THE POWERHOUSE OF THE PILBARA.

 

 

WANT TO KNOW MORE

ABOUT ARTEMIS?

 

Please Contact:

Edward Mead – Executive Director

P : +61 407 445 351

 

Wayne Bramwell – CEO

P: +61 417 953 073

 

David Tasker – Media Advisor

P : +61 433 112 936

 

Or visit the Artemis Website or

follow us on Twitter.

 

Artemis Resources Limited

Suite 1, 11 Ventnor Ave

West Perth WA

Australia, 6005

 

P : +61 8 6319 0000

E : info@artemisresources.com.au

 www.artemisresources.com.au

Twitter - @Artemis_ARV

 

BACKGROUND INFORMATION ON ARTEMIS RESOURCES

 

Artemis Resources Limited is an exploration and development company focussed on its large (≈2,400 km2) and prospective base, battery and precious metals assets in the Pilbara region of Western Australia.

 

Artemis owns 100% of the 500,000 tpa Radio Hill processing plant and infrastructure, located approximately 35 km south of the city of Karratha.  The Company is evaluating 2004 and 2012 JORC Code compliant resources of gold, nickel, copper-cobalt,  PGE's and zinc, all situated within a 40 km radius of the Radio Hill plant. 

 

Artemis have signed Definitive Agreements with Novo Resources Corp. (“Novo”), which is listed on Canada’s TSX Venture Exchange (TSXV:NVO), and pursuant to the Definitive Agreements, Novo has satisfied its expenditure commitment, and earned 50% of gold (and other minerals necessarily mined with gold) in conglomerate and/or paleoplacer style mineralization in Artemis’ tenements within 100 km of the City of Karratha, including at Purdy’s Reward (“the Gold Rights”).  The Gold Rights do not include:

 

(i)                  gold disclosed in Artemis’ existing (at 18 May 2017) JORC Code Compliant Resources and Reserves; or

(ii)                gold which is not within conglomerate and/or paleoplacer style mineralization; or

(iii)              minerals other than gold.

 

Artemis’ Mt Oscar tenement is excluded from the Definitive Agreements.  The Definitive Agreements cover 36 tenements / tenement applications that are 100% owned by Artemis.

 

Pursuant to Novo’s successful earn-in, two 50:50 joint ventures have been formed between Novo’s subsidiary, Karratha Gold Pty Ltd (“Karratha Gold”) and two subsidiaries of Artemis (KML No 2 Pty Ltd and Fox Radio Hill Pty Ltd).  The joint ventures are managed as one by Karratha Gold with Artemis and Novo contributing to further exploration and any mining of the Gold Rights on a 50:50 basis.

 

FORWARD LOOKING STATEMENTS AND IMPORTANT NOTICE

This report contains forecasts, projections and forward-looking information.  Although the Company believes that its expectations, estimates and forecast outcomes are based on reasonable assumptions it can give no assurance that these will be achieved.  Expectations, estimates and projections and information provided by the Company are not a guarantee of future performance and involve unknown risks and uncertainties, many of which are out of Artemis’ control.

 

Actual results and developments will almost certainly differ materially from those expressed or implied.  Artemis has not audited or investigated the accuracy or completeness of the information, statements and opinions contained in this announcement.  To the maximum extent permitted by applicable laws, Artemis makes no representation and can give no assurance, guarantee or warranty, express or implied, as to, and takes no responsibility and assumes no liability for the authenticity, validity, accuracy, suitability or completeness of, or any errors in or omission from, any information, statement or opinion contained in this report and without prejudice, to the generality of the foregoing, the achievement or accuracy of any forecasts, projections or other forward looking information contained or referred to in this report.

 

Investors should make and rely upon their own enquiries before deciding to acquire or deal in the Company’s securities.



NEWSLETTER REGISTRIERUNG:



Aktuelle Pressemeldungen dieses Unternehmens direkt in Ihr Postfach:
Newsletter...

Mitteilung übermittelt durch IRW-Press.com. Für den Inhalt ist der Aussender verantwortlich.

Kostenloser Abdruck mit Quellenangabe erlaubt.