Communicators

are winners!

News

20.08.2018
Cape Lambert Resources Limited: Kipushi Cobalt-Copper Tailings Project - Market Update

 

 

Kipushi Cobalt-Copper Tailings Project - Market Update

 

Highlights

 

-          Engineering Study updated;

-          Major equipment packages tendered;

-          Concrete works being tendered;

-          Design work for Leach Residue Storage Facility awarded.

 

Australian resources and investment company, Cape Lambert Resources Limited (ASX: CFE) (Cape Lambert or the Company) is pleased to provide an update on the progress at the Kipushi Cobalt-Copper Tailings Project (Project) in the Democratic Republic of Congo (DRC).

 

The Project is held by Soludo Lambert Mining SAS (Soludo Lambert), under a 50/50 joint venture arrangement with local entity Paragon Mining SARL (Paragon) and Cape Lambert. The Project involves the reprocessing of copper-cobalt tailings contained in the Kipushi Tailings Storage Facility (TSF) located near the town of Kipushi approximately 25km from Lubumbashi, refer Figure 1.

 

Figure 1: Project Location

 

As noted in the CFE June 2018 Quarterly Report, precipitation tests completed produced a mixed hydroxide precipitate (MHP) with copper and cobalt grades ranging from 22.8% - 31.9% and 9.77% - 18.4% respectively. The value of 18.4% cobalt was for a precipitate produced after the removal of copper and indicated that a higher grade cobalt MHP could be produced as an alternative to the mixed copper/cobalt MHP (refer ASX announcement dated 31 July 2018).

 

Based on this testwork, the Engineering Study recently completed by Minnovo Pty Ltd was updated to provide for the production of a copper-rich MHP and a cobalt-rich MHP separately. The production of separate products is advantages as the copper-rich MHP can be sold to copper focused companies whereas, the cobalt-rich MHP can be sold to cobalt focused companies, therefore, greatly expanding the potential buyer base.

 

The updated process flow sheet developed by Minnovo is shown in Figure 2.

 

Figure 2: Kipushi Process Flowsheet

 

The capital costs, presented in second quarter 2018 in United States dollars (USD) to an accuracy of ±35%, were updated by Minnovo for the revised process circuit, with inputs from Soludo Lambert, are summarised in Table 1.

 

Table 1: Capital Cost Estimate Summary

Description

Total (USD)

Direct Costs

 

Civils

$1,820,000

Tailings Reclamation

$125,000

Process Plant

$21,053,120

Infrastructure

$3,725,000

Mobile Fleet

$677,500

TOTAL DIRECTS

$27,400,620

Indirect Costs

 

Freight/Spares/First Fills

$3,257,823

Engineering/commissioning

$1,765,050

Owner Management

$4,294,049

TOTAL INDIRECTS

$10,246,529

Contingency

$4,110,093

TOTAL CAPITAL BUDGET

$41,757,242

 

The capital cost was developed from a number of sources as summarised in Table 2.

 

Table 2: Basis for Capital Cost Estimate

Cost Category

Source Of Cost Data

Direct Costs

Equipment costs based on budget quotations for major equipment and from recent projects/database pricing for other equipment where similar sized equipment quotes were available.

Earthworks, concrete, structural steel and platework and E&IC costs were factored against mechancial equipment costs estimated from a recent in-country copper project.

Contractor indirects and P&G costs were factored based on detailed estimate for recent in-country copper project.

Infrastructure

Building costs, detailed earthworks, fencing costs  costs were factored against mechancial equipment costs derived from similar reference factored to reflect costs estimated from a recent in-country project .

PCS and Comms in the process plant area are included in the E&IC factors for the plant.  External communications infrastructure is excluded.

Indirects

Factored based on historical Minnovo EPC contracting work.

Owners costs

Provided by Soludo Lambert.

Contingency

Allowance for Owner’s contingency of 15% of the direct Project costs.

 

The operating costs updated by Minnovo, with inputs from Soludo Lambert, presented in second quarter 2018 in United States dollars (USD) to an accuracy of ±35% are summarized in Table 2.

 

Table 2: Kipushi Operating Costs

Description

USD/tonne Tailings

Tailings Reclamation

(including fees to Gecamines)

$12.30

Processing

$45.01

Administration

$6.10

TOTAL Operating Cost

$63.41

 

The operating cost estimate was developed from a number of sources as detailed in Table 3.

Table 3: Basis for Site Operating Cost Estimate

Cost Category

Source Of Cost Data

Labour

Owner operating strategy. Labour rates are for expatriate and local labour based on 12 hour shifts.

Power

Consumption from Electrical Load List. Grid power rate advised by Soludo Lambert.

Maintenance Materials

Calculated as a percentage of direct capital costs based on benchmarking with operating plants.

Reagents and Consumables

Reagent consumption from testwork and unit prices from regional and international suppliers.

 

Following the commencement of the detailed design by Minnovo, tenders for the major pieces of equipment (thickeners, filter presses, horizontal belt filter, SO2 scrubber and clarifier) were issued, with responses due back shortly.

 

Soludo Lambert has issued the tender document for the concrete works at the leaching plant to four reputable companies operating in the DRC, with proposals due at the end of August 2018.

 

Soludo Lambert has also awarded the design of the leach residue storage facility (LRSF) to Golder Associates Africa, with a site visit to occur shortly to undertake geotechnical investigations at the proposed LRSF location.

 

Cape Lambert’s Chairman, Tony Sage, said “I am very pleased that the updated Engineering Study has provided for the production of separate cobalt-rich and copper-rich MHP products that we anticipate it will attract a much wider market of buyers and that the engineering design works are progressing with equipment and construction works out to tender.”

 

Yours faithfully

Cape Lambert Resources Limited

 

Tony Sage

Executive Chairman

 

Cape Lambert Resources Limited (ASX: CFE) is a fully funded mineral development company with exposure to iron ore, cobalt, copper, gold, uranium, lithium and lead-silver-zinc assets in Australia, Europe, Africa and South America.

 

Australian Securities Exchange

Code: CFE

 

Ordinary shares

1,011,734,914

 

Unlisted Options

15,336,363 ($0.07 exp 12 Mar 2020)

7,667,727 ($0.07 exp 19 Mar 2020)

5,250,000 ($0.04 exp 31 Mar 2020)

 

Board of Directors

Tony Sage 

Executive Chairman

 

Tim Turner 

Non-executive Director


Stefan Müller

Non-executive Director

 

Melissa Chapman
Company Secretary

 

 

Cape Lambert Contact

Investor Relations

Phone:  +61 8 9380 9555

Email: info@capelam.com.au

www.capelam.com.au

 

The Metallurgical testwork data in this presentation is based on information compiled by Mr Chris Larder who has 35 years experience in the mining and mineral processing industries. Mr Larder has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration. Mr Larder is a consultant to Cape Lambert Resources Limited and consents to the results being released in the form and context in which they appear

 

 



NEWSLETTER REGISTRIERUNG:



Aktuelle Pressemeldungen dieses Unternehmens direkt in Ihr Postfach:
Newsletter...

Mitteilung übermittelt durch IRW-Press.com. Für den Inhalt ist der Aussender verantwortlich.

Kostenloser Abdruck mit Quellenangabe erlaubt.